Status
|
Activity
|
Comment
|
|
|
November 13, 2002
|
Received unsolicited proposal
|
Submitted by Fluor Enterprises, Inc.
|
|
|
July 25, 2003
|
Issued request for competing proposals and qualifications
|
In response to the unsolicited proposal submitted by Fluor, TxDOT requested competing proposals.
|
|
|
September 23, 2003
|
Deadline to receive request for proposal and qualifications
|
The three private sector firms submitted competing proposals and qualifications -- Cintra-Zachry, Fluor Enterprises and Trans-Texas Express.
|
|
|
September 24 - October 29, 2003
|
Evaluated proposal and developer qualifications
|
All three private sector firms were advanced to the next stage of the selection process.
|
|
|
Fall 2003 - Summer 2004
|
Industry review process
|
This included drafting a request for detailed proposals, meeting with, and receiving comments from the proposers.
|
|
|
February 2004
|
Notice of Intent published in federal and state registers
|
This is the official notification that TxDOT intends to begin an environmental study for this element of the Trans-Texas Corridor.
|
|
|
April 7 - June 15, 2004
|
Spring 2004 public meetings
|
TxDOT held 26 public meetings throughout the study area to introduce this project and solicit public comments.
|
|
|
April 29, 2004
|
Issued request for detailed proposals
|
TxDOT formally asked the three proposers to submit detailed proposals.
|
|
|
August 23, 2004
|
Deadline to submit detailed proposals
|
The three shortlisted firms -- Cintra-Zachry, Fluor Enterprises and Trans-Texas Express -- submitted detailed proposals.
|
|
|
October 19 - November 18, 2004
|
Fall 2004 public meetings
|
TxDOT held 44 public meetings throughout the study area to introduce corridor alternatives and solicit public comments on TTC-35.
|
|
|
Fall 2004
|
Evaluations of detailed proposals
|
TxDOT performed comprehensive review of each proposal to determine the best value proposal for the state.
|
|
|
December 16, 2004
|
Transportation Commission action
|
The Commission approved the selection of Cintra-Zachry as the developer.
|
|
|
Late 2004-Early 2005
|
Finalized terms of the comprehensive development agreement (CDA)
|
TxDOT and Cintra-Zachry discussed terms and conditions of the CDA.
|
|
|
February 7 - March 31, 2005
|
Spring 2005 public meetings
|
TxDOT held 47 public meetings throughout the study areas to gather public comments on possible routes for TTC-35.
|
|
|
March 11, 2005
|
CDA signed
|
TxDOT and Cintra-Zachry agree on long-term strategic partnership.
|
|
|
June 3, 2005
|
Issued notice to proceed for initial scope of work
|
Cintra-Zachry begins work on master development plan and financial plan.
|
|
|
April 4, 2006
|
Draft Environmental Impact Statement (DEIS) signed
|
DEIS evaluates alternatives and identifies a corridor for future studies.
|
|
|
July 10 - August 10, 2006
|
Summer 2006 public hearings
|
TxDOT held 54 public hearings throughout the study area to gather comments on the recommended study area. More than 6,000 comments were received.
|
|
|
September 28, 2006
|
Master Development Plan (MDP) unveiled
|
The MDP outlines the phasing and implementation of TTC-35. The MDP will be updated based on the findings of the environmental studies.
|
|