Trans-Texas Corridor
Home | Site Tools (downloads)  
decorative graphic
About TTCTTC ProjectsGet InvolvedGet the FAQsTTC FinancingTTC & MeNews &LlibraryComments/Mailing List
decorative graphic
decorative graphic
TTC Projects Upon clicking the navigation items below, subnavgtion will appear (where applicable). You may need to manually activate your screen reader to continue reading the page.
 
 
Did You Know...

Do you have a question?
Check out our FAQ section.


Download the free Adobe Acrobat Reader

PDF documents require Adobe Reader for viewing.

decorative graphic decorative graphic
 

decorative graphic

I-69/TTC (Northeast Texas to Mexico)

ENVIRONMENTAL STUDY TIMELINE

Activity Status
Environmental process begins Jan. 2004

Public involvement (information meetings) Jan. 2004

Preliminary corridor alternatives identified Feb. 2004-May 2005

Reasonable corridor alternatives identified Summer 2005

Public involvement (information meetings) Jul. - Aug. 2005

Prepare draft environmental impact statement Ongoing

Public hearings on the DEIS Feb 4 - March 4, 2008

Complete final environmental impact statement Anticipated Winter 2007/Spring 2008

Federal Approval – (record of decision) Anticipated 2008

 